Progress claims: what goes on one, and which law covers it.

Checked against each state’s Act and regulator on 31 October 2026 · A summary, not legal advice · The calculator works in your browser; nothing you enter is sent anywhere.

The contract, stage by stage

This claim

Contract
Work done to date
Work done
Claimed after this one

A progress claim asks to be paid for the work done so far on a contract. Under each state’s security of payment law it has to identify the work and state the amount. In NSW and Victoria it must also say it’s made under the Act, and in Queensland it must ask for payment.

Whether that law covers your claim depends on who you’re claiming from. Claiming from a builder or a business, it does in all three states. Claiming from a homeowner for work on the home they live in, it does in NSW, but not in Queensland or Victoria.

Which law covers your claim

StateClaiming from a builder or businessClaiming from a homeowner, for the home they live in
NSWBuilding and Construction Industry Security of Payment Act 1999The same Act. Its old exemption for owner-occupiers was repealed, and the NSW Government says it now applies to owner-occupier construction contracts
QueenslandBuilding Industry Fairness (Security of Payment) Act 2017Not that Act (section 61). The QBCC’s rule applies: progress payments must match the work completed
VictoriaBuilding and Construction Industry Security of Payment Act 2002Not that Act, unless the owner is in the business of building homes. Your domestic building contract sets the payments
Checked 31 October 2026 against each Act and regulator; sources at the end. A summary, not legal advice.

Either way, claim only for work you’ve done. On a homeowner job, follow the payment schedule in your contract: in NSW, a contract over $20,000 must set one out, as fixed payments after set stages, payments as the work is done, or both.

What the claim must say, and when you can send it

NSWQueenslandVictoria
On the claimThe work it covers, the amount, and that it’s made under the ActThe work it covers, the amount, and a request for paymentThe work it covers, the amount, and “This is a payment claim under the Building and Construction Industry Security of Payment Act 2002”
EarliestThe last day of the month the work started, then the last day of each month after, or an earlier date in the contractEach reference date in the contract, or the last day of each month you workThe last day of the month the work started, then the last day of each month after, or an earlier date in the contract. December work: from 22 December, or 31 January for work after 21 December
Latest12 months after the work was last done, or later if the contract says6 months after all the work is finished, or later if the contract says6 months after practical completion, or later if the contract says
If they won’t pay it allThey must send a payment schedule within 10 business daysWithin 15 business daysWithin 10 business days
When it’s due, if the contract doesn’t say15 business days from a principal; 10 from a head contractor on residential work, 20 on other work10 business days. Subcontracts can’t set more than 25, commercial building contracts no more than 15The contract’s date, which can’t be more than 20 business days after the claim
The rules for claims under each state’s security of payment Act. Your contract can set shorter times.

In all three states, a “pay when paid” clause has no effect: whoever you claim from can’t hold your payment until they’re paid themselves. A head contractor claiming from the owner in NSW, or on a non-residential job in Queensland, also has to attach a supporting statement saying their subcontractors have been paid.

How to write one

There’s no set form. A progress claim that works in every state has:

  1. A heading and a number, such as “Progress claim 3”, with your business name, ABN and the date. If you’re registered for GST, it’s also your tax invoice, so it needs the ATO’s details; our invoice templates have them.
  2. The contract it’s under: your quote or contract number and the site address.
  3. The work, stage by stage: each stage’s value, how much is done, and the value of the work done to date.
  4. The sum: work done to date, less what you’ve already claimed (the deposit included), is this claim.
  5. The words your state needs, from the table above. In Queensland, “Please pay this amount by [date]” does it.
  6. Evidence: the NSW Government suggests attaching statements of the work done, completion certificates, delivery dockets and photographs.

The calculator at the top does the sum. Here’s the same claim written out: a carpenter framing a house for a builder, under a $48,400 subcontract.

Example data. The figures are made up, and include GST.
StageValueDoneWork done to date
Floor frame$8,800.00100%$8,800.00
Wall frames$17,600.00100%$17,600.00
Roof trusses and battens$15,400.0060%$9,240.00
Fascia and eaves$6,600.000%$0.00
Work done to date$35,640.00
Less claims 1 and 2−$26,400.00
This claim$9,240.00

After this claim, 73.6% of the subcontract is claimed, matching the 73.6% of the work that’s done. That’s the test Queensland applies to homeowner jobs: the QBCC’s example is that you can’t claim more than 50% of the price, the deposit included, until at least 50% of the work on site is done.

In Deftara Quoting

Raise each progress claim against the job your customer accepted. The job keeps track of what’s left to bill, and every claim comes with a reminder to claim only for work already done, quoting the rule in NSW and Queensland. See how quoting and invoicing works.

More for trades

Sources

Talk to us

Billing jobs in stages?

Deftara Quoting raises the deposit when your customer accepts and tracks what’s left to bill on every job. Tell us how you invoice now.

We need your name and an email or a phone number. The rest helps us prepare.

We only use these details to reply to you. Privacy

What happens next

  1. Talk

    Tell us how the business runs and what you use now.

  2. Match

    We pick the closest app and tell you what would change.

  3. Set up

    Your branding, your data and your team’s logins, at no cost.

  4. Go live

    Your team starts using it on its own copy.

Prefer email? Send a recent quote to hello@deftara.com.au, with the prices blanked out if you like.