A progress claim asks to be paid for the work done so far on a contract. Under each state’s security of payment law it has to identify the work and state the amount. In NSW and Victoria it must also say it’s made under the Act, and in Queensland it must ask for payment.
Whether that law covers your claim depends on who you’re claiming from. Claiming from a builder or a business, it does in all three states. Claiming from a homeowner for work on the home they live in, it does in NSW, but not in Queensland or Victoria.
Which law covers your claim
| State | Claiming from a builder or business | Claiming from a homeowner, for the home they live in |
|---|---|---|
| NSW | Building and Construction Industry Security of Payment Act 1999 | The same Act. Its old exemption for owner-occupiers was repealed, and the NSW Government says it now applies to owner-occupier construction contracts |
| Queensland | Building Industry Fairness (Security of Payment) Act 2017 | Not that Act (section 61). The QBCC’s rule applies: progress payments must match the work completed |
| Victoria | Building and Construction Industry Security of Payment Act 2002 | Not that Act, unless the owner is in the business of building homes. Your domestic building contract sets the payments |
Either way, claim only for work you’ve done. On a homeowner job, follow the payment schedule in your contract: in NSW, a contract over $20,000 must set one out, as fixed payments after set stages, payments as the work is done, or both.
What the claim must say, and when you can send it
| NSW | Queensland | Victoria | |
|---|---|---|---|
| On the claim | The work it covers, the amount, and that it’s made under the Act | The work it covers, the amount, and a request for payment | The work it covers, the amount, and “This is a payment claim under the Building and Construction Industry Security of Payment Act 2002” |
| Earliest | The last day of the month the work started, then the last day of each month after, or an earlier date in the contract | Each reference date in the contract, or the last day of each month you work | The last day of the month the work started, then the last day of each month after, or an earlier date in the contract. December work: from 22 December, or 31 January for work after 21 December |
| Latest | 12 months after the work was last done, or later if the contract says | 6 months after all the work is finished, or later if the contract says | 6 months after practical completion, or later if the contract says |
| If they won’t pay it all | They must send a payment schedule within 10 business days | Within 15 business days | Within 10 business days |
| When it’s due, if the contract doesn’t say | 15 business days from a principal; 10 from a head contractor on residential work, 20 on other work | 10 business days. Subcontracts can’t set more than 25, commercial building contracts no more than 15 | The contract’s date, which can’t be more than 20 business days after the claim |
In all three states, a “pay when paid” clause has no effect: whoever you claim from can’t hold your payment until they’re paid themselves. A head contractor claiming from the owner in NSW, or on a non-residential job in Queensland, also has to attach a supporting statement saying their subcontractors have been paid.
How to write one
There’s no set form. A progress claim that works in every state has:
- A heading and a number, such as “Progress claim 3”, with your business name, ABN and the date. If you’re registered for GST, it’s also your tax invoice, so it needs the ATO’s details; our invoice templates have them.
- The contract it’s under: your quote or contract number and the site address.
- The work, stage by stage: each stage’s value, how much is done, and the value of the work done to date.
- The sum: work done to date, less what you’ve already claimed (the deposit included), is this claim.
- The words your state needs, from the table above. In Queensland, “Please pay this amount by [date]” does it.
- Evidence: the NSW Government suggests attaching statements of the work done, completion certificates, delivery dockets and photographs.
The calculator at the top does the sum. Here’s the same claim written out: a carpenter framing a house for a builder, under a $48,400 subcontract.
| Stage | Value | Done | Work done to date |
|---|---|---|---|
| Floor frame | $8,800.00 | 100% | $8,800.00 |
| Wall frames | $17,600.00 | 100% | $17,600.00 |
| Roof trusses and battens | $15,400.00 | 60% | $9,240.00 |
| Fascia and eaves | $6,600.00 | 0% | $0.00 |
| Work done to date | $35,640.00 | ||
| Less claims 1 and 2 | −$26,400.00 | ||
| This claim | $9,240.00 | ||
After this claim, 73.6% of the subcontract is claimed, matching the 73.6% of the work that’s done. That’s the test Queensland applies to homeowner jobs: the QBCC’s example is that you can’t claim more than 50% of the price, the deposit included, until at least 50% of the work on site is done.
In Deftara Quoting
Raise each progress claim against the job your customer accepted. The job keeps track of what’s left to bill, and every claim comes with a reminder to claim only for work already done, quoting the rule in NSW and Queensland. See how quoting and invoicing works.
More for trades
- TPARWhether you lodge a Taxable payments annual report for subbies, what to report, and the 28 August due date.
- Free invoice templatesTax invoice and no-GST invoice, with a contract running total for deposits and progress claims.
- Home warranty insurance by stateWhen a job needs it, what it costs, and the deposit caps.
- Letter of demand templateFor an invoice that still isn’t paid, and where to go next in each state.
- Trade toolsRoof pitch, decking, stairs, fences, downpipes, charge-out rates and more.
Sources
- Building and Construction Industry Security of Payment Act 1999 (NSW), version from 20 August 2024: sections 7, 11, 12, 13 and 14. Checked 31 October 2026.
- NSW Government: making a payment claim and about Security of Payment, checked 31 October 2026.
- NSW Government: guide to providing home building contracts, last updated 11 June 2026, checked 31 October 2026.
- Building Industry Fairness (Security of Payment) Act 2017 (Qld), reprint from 28 April 2026: sections 61, 68, 73 and 76. Checked 31 October 2026.
- QBCC: request payment, last reviewed 31 August 2021, and QBCC: deposits and progress payments, last reviewed 27 June 2025. Checked 31 October 2026.
- BPC: making a payment claim under the SOP Act, last updated 22 October 2026, and responding to a payment claim, last updated 30 June 2026, and changes affecting construction contracts, last updated 30 June 2026. Checked 31 October 2026.