A deck, balcony, landing or stair needs a balustrade where someone could fall 1 m or more. On a deck, balcony or landing it must be at least 1 m high. Along a stair it must be at least 865 mm above the nosings. No gap may let a 125 mm ball through.
A stair that rises 1 m or more also needs a handrail on at least one side, its top at least 865 mm above the nosings. Over a fall of more than 4 m, rails between 150 and 760 mm above the floor must not be climbable.
When you need a balustrade
The NCC calls it a barrier. Clause 11.3.3 requires one along the side of any trafficable surface where it’s possible to fall 1 m or more, measured from that surface to the surface beneath. That covers stairs and ramps, floors, balconies, decks, verandahs and landings, roof spaces people can get to, and paths to a building.
Measure from the floor to the surface beneath; Figure 11.3.3a in the NCC shows how. A retaining wall needs a barrier only when it’s part of, or right beside, a path to a building from the road or between buildings.
How high
| Where | At least | Measured from |
|---|---|---|
| Deck, balcony, verandah, landing, hallway, path | 1,000 mm | The floor |
| Stair flight or ramp | 865 mm | The nosings of the treads, or the ramp floor |
| Inside edge of a stair landing, 500 mm long or less | 865 mm | The landing floor |
Gaps and climbing
- 125 mm: no opening may let a 125 mm sphere through, decorative balustrades included. On a stair, measure the opening above the line of the nosings (11.3.4(4)).
- 40 mm: where the balustrade is fixed to the face of the deck, landing or stair, the gap between it and the edge of the floor can’t be more than 40 mm, measured horizontally (11.3.4(5) and (6)).
- Over a 4 m fall: horizontal elements between 150 mm and 760 mm above the floor must not make it climbable (11.3.4(8)).
- Attic and storeroom stairs used now and then can have openings up to a 300 mm sphere, or a top rail and a middle rail no more than 460 mm apart (11.3.4(7)).
Wire balustrades meet the 125 mm rule only when built to 11.3.6: wire size, spacing, post spacing and tension or deflection from the NCC’s Tables 11.3.6a to 11.3.6c. Glass balustrades also have to meet the glazing rules (H1D8). Every balustrade has to carry the loads in AS/NZS 1170.1.
Handrails
Under 11.3.5, a stair or ramp needs a handrail along at least one side, for the full length of the flight, with its top at least 865 mm above the nosings or the ramp floor. It has to be continuous, with nothing on or above it that breaks your grip, apart from newel posts, ball stanchions and the like. The top rail of a balustrade can be the handrail if you can grip it.
You don’t need one where the stair or ramp changes level by less than 1 m, on a landing, or on winders where a newel post gives a handhold. Our stair calculator works out the risers and goings and flags when a handrail is needed.
Windows
- Bedrooms: where the floor is 2 m or more above the ground outside, an openable window needs protection unless its opening is at least 1.7 m above the floor. A restrictor or screen must stop a 125 mm sphere and resist a 250 N push. If it can be removed or unlocked, it needs a child-resistant release, and the window also needs an 865 mm barrier inside (11.3.7).
- Other rooms: where the floor is 4 m or more above the ground, an openable window needs a barrier at least 865 mm high, with no 125 mm openings and nothing climbable between 150 and 760 mm (11.3.8).
Pricing the job
Price a balustrade by the lineal metre, with posts, gates and corners as items. Deftara Quoting keeps those prices in your price book and adds your markup on every line. See quoting for carpenters. The decking calculator prices the deck itself.
This page summarises the NCC’s deemed-to-satisfy rules for houses (Class 1 and 10 buildings). Your state can vary them, and pool barriers have their own rules (NCC H7D2). Check the plans and your certifier before you build.
More for trades
- Stair calculatorRisers, goings and stringer length, checked against the NCC stair limits.
- Decking calculatorBoards, joists and screws, and the cost from your own prices.
- Home warranty insurance by stateWhen a job needs it, what it costs, and the deposit caps.
- Trade toolsRoof pitch, decking, stairs, fences, bricks, charge-out rates and more.
Sources
- NCC 2025, ABCB Housing Provisions Part 11.3: barriers and handrails, clauses 11.3.3 to 11.3.8. Checked 1 November 2026.
- NCC 2022, ABCB Housing Provisions Part 11.3: the same heights, gaps and window rules. Checked 1 November 2026.