The NCC rules for eaves gutters
For houses, NCC Housing Provisions Part 7.4 sets these, the same in NCC 2022 and NCC 2025:
- Gutter size from Table 7.4.3a, by the rainfall where the house is and the roof area each downpipe drains.
- At most 12 m of gutter to each downpipe, with downpipes as close as possible to valley gutters (7.4.5).
- A fall of at least 1:500: 2 mm a metre, so 24 mm over a 12 m run (7.4.4).
- Brackets at stop ends, at corners and no more than 1.2 m apart (7.4.4).
- Overflow measures sized for the 1% AEP rainfall, either continuous, like a front-face slotted gutter (slots of at least 1,200 mm² a metre, their lower edge at least 25 mm below the top of the fascia, 7.4.6), or one at each downpipe (7.4.7). Not needed on a verandah or eave over 450 mm wide that’s unlined, or raked with its lining sloping away from the house.
- Valley gutters only on roofs steeper than 12.5°, with at least 15 mm of freeboard.
Box gutters aren’t covered: the NCC points to AS/NZS 3500.3 for their sizes, falls and overflows. Western Australia has its own variation to 7.4.5.
Gutters and downpipes
| Type | Gutter | Cross-section, at least | Downpipes |
|---|---|---|---|
| A | Medium rectangular | 6,500 mm² | 75 or 90 mm round, 100 × 50 or 100 × 75 mm |
| B | Large rectangular | 7,900 mm² | 75 or 90 mm round, 100 × 50 or 100 × 75 mm |
| C | 115 mm D | 5,200 mm² | 75 or 90 mm round, 100 × 50 or 100 × 75 mm |
| D | 125 mm D | 6,300 mm² | 75 or 90 mm round, 100 × 50 or 100 × 75 mm |
| E | 150 mm D | 9,000 mm² | 90 mm round, 100 × 50 or 100 × 75 mm (not 75 mm round) |
Design rainfall in the capital cities
| City | Gutters (5% AEP) | Overflows (1% AEP) |
|---|---|---|
| Brisbane | 236 mm/h | 306 mm/h |
| Darwin | 233 mm/h | 274 mm/h |
| Sydney | 201 mm/h | 262 mm/h |
| Canberra | 143 mm/h | 192 mm/h |
| Melbourne | 132 mm/h | 187 mm/h |
| Perth | 129 mm/h | 172 mm/h |
| Adelaide | 120 mm/h | 174 mm/h |
| Hobart | 86 mm/h | 120 mm/h |
How it works it out
- It takes the rainfall for the place you pick and uses the next row up in Table 7.4.3a (201 mm/h in Sydney uses the 225 mm/h row).
- It starts with enough downpipes for no more than 12 m of gutter each.
- It shares the roof area equally between them and uses the next column up (45 m² uses the 50 m² column).
- If your gutter isn’t allowed in that cell, it adds a downpipe and tries again.
Two readings of the table are ours. A cell names the smallest gutter of each shape, so a bigger one of the same shape passes too: a 125 mm D gutter where the cell says 115 mm D. And in the 225 mm/h row, the 50 m² cell lists only rectangular gutters while the 60 m² cell allows a 150 mm D, so we allow the 150 mm D at 50 m² as well.
The NCC’s table doesn’t say how to measure the roof area. A roof’s sloping area is bigger than its plan area, so using the sloping area is the safer side. The roof sheet calculator gives it.
A worked example
A 15 m gutter in Sydney taking 90 m² of roof:
- 15 m needs at least 2 downpipes, 7.5 m of gutter each, and 45 m² of roof each.
- Sydney’s 201 mm/h uses the 225 mm/h row; 45 m² uses the 50 m² column, which says “A or B”. A medium rectangular gutter works with 2 downpipes.
- A 115 mm D gutter isn’t in that cell, so it needs 3 downpipes (30 m² each, “A or C”).
- The gutter falls at least 30 mm over the 15 m, on at least 14 brackets, with overflows sized for 262 mm/h.
From roof to price
That’s the job Deftara Quoting does for roofers: gutters by the metre and downpipes, brackets and stop ends as items, each priced as your cost plus your markup. Then check your markup and margin.
More for trades
- Roof sheet calculatorSheet length, sheet count, ridge, barge and gutter for a gable or skillion roof.
- Roof pitch calculatorRise and run in millimetres to degrees and rafter length.
- Roof sarking calculatorWhen tiles need sarking under the NCC, and how many rolls.
- Free quote templatesWord, Excel and PDF, with a roofing version for sheets, flashings and gutters.
Sources
- NCC 2025, ABCB Housing Provisions Part 7.4: clauses 7.4.1 and 7.4.3 to 7.4.7, Tables 7.4.3a to 7.4.3d. Checked 1 November 2026.
- NCC 2022, ABCB Housing Provisions Part 7.4: the same tables. Checked 1 November 2026.